In the construction of Namangan Square houses, tunnel formwork is used — this is a set of special equipment that is used for concrete tunnel bays and other structures based on them. Using formwork elements, borders can be set. Subsequently, this form is filled with concrete. After the solidification of the mass, the formwork is dismantled and a finished structure is obtained.
Benefits of this method:
— ability to complete all necessary construction work;
— guarantee of obtaining perfect accuracy;
— excellent quality of the finished structure;
— improving such characteristics as solidity, integrity, reliability.
Construction progress of Namangan Square residential complex
Period: 01.08.20 — 06.08.20
✔️ Tunnel form work is in progress for second floor block A03
✔️ Rebarwork for slab is in progress in for second floor block A03
✔️ Installation of columns and shear walls work is in progress for third floor block A03
✔️ Shear walls and electrical work is in progress for third floor block A03